Heartland Transmission



New Russell Substation

 

    Download full resolution PDF            
   
     

   

 

 

 

Overview

AltaLink is proposing to build a new substation called Russell in the Pincher Creek area as part of the larger Southern Alberta Transmission Reinforcement. This substation is proposed to be located next to TransAlta’s existing Castle River Substation.

Project Details

New substation
Name:
Russell 632S
Voltage: 138 kV (138,000 volts)
Size: 120 metres by 60 metres (394 by 147 feet)
Location: LSD 15 - Sec.35 - Twp.6 - Rge.1 - W5M

Transmission line work
AltaLink is proposing to reconfigure the existing 138 kV line in the area, called 170L, remove approximately 60 metres of the 170L line and salvage an existing 138 kV line, called 170AL.

Project schedule

April/May 2010      Notify and consult with stakeholders and landowners
  June 2010      File application with Alberta Utilities Commission (AUC) for regulatory review  
   and approval  
              Q1 2011    Start project construction if approval is granted by AUC
 September 2011      Complete project construction