AltaLink



Adjust text size
  Big   Small  

Heartland Transmission



East Palliser Transmission Project

 

    Download full resolution pdf          
   
     

   
    The routes in this map represent 
    potential route options. If the
    project is approved, only one line
    will be built.


Thank you to everyone who attended our open houses. Your input is important to us.

Overview
AltaLink is proposing to construct and operate two new transmission lines, a new switching station in Cypress County and to make additions to the Bowmanton and Cypress substations to connect NaturEner’s proposed Wild Rose 1 and 2 Wind Power Projects to the electric system. Each wind power project will provide up to 200 megawatts (MW) each of additional wind power to the province’s electric system.

Project Details
AltaLink is proposing to:
      • Build approximately 75 kilometres of new transmission line between the proposed 
        Bowmanton Substation and the existing Cypress Substation (East Palliser North).
      • Build approximately 35 kilometres of transmission line between NaturEner’s 
        proposed Wild Rose 1 Substation  and a proposed Elkwater Switching Station. The 
        Elkwater Switching Station will also connect to NaturEner’s proposed Wild Rose 2 
        Wind Power Project (East Palliser South).
      • Build a new switching station, to be called Elkwater, near Woolchester.
      • Add equipment to the proposed Bowmanton and Cypress Substations.

**** For more information on the 138 kV Transmission Line Rebuild, please visit the newsletter and maps page by clicking here.

Status of project: Consultation underway 

Project schedule

May to July 2010      Notify and consult with stakeholders
Summer 2010      File application with Alberta Utilities Commission 
   (AUC) for its review
                            Fall 2011      Start project construction if approval is granted by AUC

To view the newsletter and maps for this project click here.