Heartland Substation and Transmission Line Development

 
Overview

AltaLink is proposing to build:

  • a new 500 kV/240 kV substation, named Heartland 12S, as well as a telecommunications tower within the proposed substation site
  • approximately 22 kilometres (km) of new 240 kV transmission line from the new substation to an existing transmission line, named 942L/943L

These proposed facilities are located north of Fort Saskatchewan in the Heartland Industrial Area.

The Heartland Substation 12S will be the termination point for the proposed 500 kV double circuit transmissio line associated with the Heartland Transmission Project, if it is approved by the Alberta Utilities Commission (AUC). More information about the Heartland Project can be found at www.heartlandtransmission.ca. The new 240 kV transmission line will distribute power from the Heartland 500 kV line to northeastern Alberta.

Project Details

Proposed Substation:

  • Will be named the Heartland Substation 12S
  • Will include four, single phase 500/240 kV transformers with associated equipment
  • Will include a teleommunications tower approximately 50 metres (164 feet) tall
  • Room will be left for future expansion

.
Proposed Transmission Line:

  • approximately 22 km of 240 kV transmission line from a new substation (Heartland 12S) to an existing line, named 942L/943L
  • Will be built with steel structures that range from about 44 to 57 metres high and about 21 metres wide
  • Structures will be double circuit, meaning they will have the capacity to carry three sets of two wires on each side

 

Project Schedule

Winter/Spring 2010    Notify and consult with landowners, residents and occupants.
January 2010     Open house scheduled.
Spring 2010     Anticipated filing date of Facility Application with the Alberta Utilities Commission (AUC).
 Summer 2011     Start of substation construction if approval is received from the AUC.
       Summer 2012   Start of 240 kV transmission line construction if approval is received from the AUC.
           Early 2013   End of construction for substation and 240 kV transmission line.

.
.