AltaLink



Adjust text size
  Big   Small  

Heartland Transmission



Ellerslie to Clover Bar Reinforcement

 

    Download full resolution PDF

Overview

The Alberta Electric System Operator (AESO) has requested AltaLink reinforce the transmission system between the Ellerslie and Clover Bar substations in the Edmonton and Sherwood Park areas.

Project Details

Ellerslie 89S substation

  • An existing 240 kV (240,000 volts) transmission line, named 947L, was de-energized
        from the electric system between the East Edmonton substation and the Ellerslie
        substation in 2007. The proposal is to re-energize this portion of the line and connect
        this circuit to separate breakers in the Ellerslie substation with new wires from the first
        tower structure. This work will be within the existing substation fenced site.


East Edmonton 38S to Clover Bar E987S substations

  • The existing transmission line, named 783L/915L, between the East Edmonton
        and Clover Bar  substations is a double circuit line, with one circuit energized
        at 240 kV and the other at 138 kV. The circuit that is currently energized at
        138 kV will be energized at 240 kV.
  • An existing single circuit transmission line, named D998L, south of Clover Bar is
        currently not energized and will be energized at 138 kV. Maintenance to be
        done on the D998L includes replacing two structures on each side of the North
        Saskatchewan river with taller steel lattice towers. Other structures may also be
        replaced.
  • The East Edmonton substation will require a new breaker and two new steel poles.
        This work will be within the existing substation fenced site.


Clover Bar E987S substation

  • Approximately 150 metres of new 240 kV line and three steel lattice towers will be built
        on a newright-of-way to the north of the Clover Bar substation.
  • The Clover Bar substation will require new breakers and a 240 kV transformer.
        EPCOR will be completing this work at the Clover Bar substation.


Project schedule

September 2008 - March 2009       Consultation with stakeholders 
March 3, 2009       File application with the AUC 
Summer 2009       Proposed start of project (pending AUC approval) 
October 2009       In-Service Date

 

AltaLink Stakeholder Information Brochure