West Brooks to East Medicine Hat (Now known as Cassils to Bowmanton)
New transmission line and substations
![]() |
Find your property
|
| Download full resolution map PDF |
Overview
The West Brooks to East Medicine Hat project is one of many pieces identified in SATR. The purpose of this reinforcement is to connect wind energy to Alberta’s electrical grid and to strengthen the transmission system in the area.
We have identified our preferred route and alternate routes for the new transmission line. AltaLink began consulting for this project in the spring of 2009. Through public consultation, AltaLink has received valuable stakeholder input that has helped us identify the preferred and alternate routes. AltaLink’s consultation program included six project open houses and more than 235 face-to-face meetings and 440 telephone conversations with stakeholders. Thank you for participating in our consultation process – your input is important to us.
Please note we have named the substations included in this project and the project name has changed to Cassils to Bowmanton.
The project includes:
• a new transmission line from west of Brooks to east of Medicine Hat
• a new substation located west of Brooks (Cassils Substation)
• a new substation located northeast of Medicine Hat (Bowmanton Substation)
Project Details
Communities involved: Town of Brooks, City of Medicine Hat, County of Newell, County of Cypress
Length of line: Approximately 125 to 151 kilomometres in length (depending on the final route)
End points: From west of Brooks to east of Medicine Hat
Line Voltage: 240 kV (240,000 volts)
Structure type: Double circuit, steel lattice tower
Right-of-way: 60 metres
Status of project: Consultation underway
Project schedule
| Spring/Summer 2009 | Notify and consult with stakeholders and landowners |
| Winter 2009 | Follow-up consultation |
| Summer 2010 | File Application with Alberta Utilities Commission for review |